NEW BUILDING PROJECT

Since 2019, we have been working towards building a new facility, to better serve our community. In late 2019, we purchased property at 24303 Hwy 321 in Lenoir City, TN and began raising funds and making plans to build.  

  

We are so grateful for all the help and support we have already received from the community and our financial partners, which include The Charles and Sue Fouche Foundation, Radio Systems Corporation, The Joanne W. Gauntt Charitable Foundation, The Leslie L. Alexander Foundation, The Good Neighbor Shoppe, ASPCA Spay/Neuter Alliance, and Dogs Trust, USA, plus many others.

In May of 2023, we selected 1st Choice Total Solutions, Inc of Greenback, TN to complete our new facility. We broke ground on construction on July 31,2023, and we hope to see construction completed by Fall 2024.

In late 2023, we reached our goal of $900,000 in funds raised! This will allow us to complete our new facility with no mortgage and allow us to focus our fundraising going forward on caring for pets in our community, however, we are now in need of funding to build a fence to keep pets safe in our parking lot. See below for ways to donate.

Fundrasing goal: $30,000

We are fundraising to build a fence for our parking lot to keep pets safe when getting in and out of their owners' vehicles. We need to raise approximately $30,000 to add this safety feature to our grounds. To meet this goal, we are again offering to memorialize your pet or loved one in our brick memorial garden. 

DONATION SUGGESTIONS

$150   4 x 8 Walkway Brick - personalized message

              Up to 3 lines & up to 14 characters per line

$300   8 x 8 Walkway Brick - personalized message

               Up to 6 lines & up to 14 characters per line

               (add 2 lines per section on form)

               

 

bricks.jpg

Donate Now

to help us build a fence to keep pets safe on our grounds

PayPal ButtonPayPal Button

* TO DONATE, YOU MUST ALSO HIT DONATE BUTTON AND FOLLOW THE STEPS INDICATED

NEW FACILITY FLOOR PLAN

ppaw 51x68 building only.png
IMG_0420.jpg
PPAW-new-logo-teal.png

Completed March 2024: Excavation, Site Prep, and Compaction

April 16, 2024: Foundation Poured

IMG_8627.jpg
image0000.jpg

April 25, 2024: Exterior Walls completed

-2114101954511635671.jpg

May 2,2024: Roof completed

building 3.jpg

May 6, 2024: Framing completed

May 13, 2024: Siding Complete
May 28, 2024: Rough in electrical, HVAC, plumbing

dry wall lobby.jpg
hallway.jpg

July 3, 2024: Drywall complete

July 8, 2024: Interior Paint and exterior paint underway
July 12,2024: Sidewalk complete

20240812_113537.jpg

August 12, 2024: Paving underway 